Witset Canyon Revitalization Project
June 10, 2020 Council Meeting Update:
Decision was made to remove Option B due to the high costs associated with such a large scale project and the potential negative impact to such an archaeological sensitive site.
Cost breakdown is as follows:
Option A: $374,935
Option B: $1,915,000
Option C: $554,587
In order to further reduce costs, the value above does not include a paved parking area, nor the cost of a picnic shelter. Once this project is complete, Council will review and a separate project for this purpose could be done in the future.
Based on the new information, please vote for your favorite option below.
Your feedback has been submitted
For more information on this project please contact economic.development@witset.ca